M.R. Svinkin
VibraConsult, Cleveland, Ohio, USA
R. Skov
CP Test a/s, Vejle, Denmark
ABSTRACT: Knowledge of pile capacity over a long
period of time after the end of initial driving is important for proper
design, construction and estimation of the cost of pile foundations. In
this paper, assessment of pile capacity as a function of time has been
performed for cohesive soils. On the basis of an existing formula, a new
relationship between pile capacity and time after pile installation has
been derived. This relationship takes into account pile capacity at the
end of driving and an actual time after pile installation. Derived
results can be used as a guide for evaluation of long term capacity of
piles in cohesive soils.
1 INTRODUCTION
Piles have to withstand design loads for a long
period of time. Therefore the consequences of soil modification around
the pile are essential with respect to changes of pile capacity. During
pile installation, the soil around the pile experiences plastic
deformations, remolding, and pore pressure changes. Excess pore water
pressure developed during driving reduces the effective soil shear
strength and ultimate pile capacity. After the completion of pile
driving, soil reconsolidation in cohesive soils, manifested by the
dissipation of excess pore pressure at the soil-pile interface zone, is
usually accompanied by an increase in pile capacity (soil set-up). The
amount of increase in pile capacity and the time required for return of
equilibrium conditions depend on soil properties and pile
characteristics. For example, the disturbed zone around a pile is more
or less proportional to the soil volume displaced during driving and
dissipation of excess pore water pressure occurs faster in friction
soils.
The phenomenon of time-dependent strength gain in
cohesive soils related to pile driving has been studied and published,
for example, Fellenius et al. (1989), Randolph et al. (1979), Skov
& Denver (1988), Seed & Reese (1955), Svinkin et al. (1994),
Thorburn & Rigden (1980), Tomlinson (1971), Wardle et al. (1992),
and others.
Assessment of pile capacity as a function of time is,
of course, important in the design and construction of pile foundations.
Having knowledge of general tendencies of pile capacity with time after
driving would certainly be beneficial in economical standpoint. Such
information may be used during construction to reduce the design
penetration and pile capacity at the end of initial driving and also to
choose relevant time for dynamic testing at restrikes or static loading
test. In this paper, an attempt is made to present the relationships
between pile capacity and elapsed time after the end of initial driving
(EOID) for cohesive soils and to show some benefits for estimation of
pile capacity from this approach.
2 EXISTING FORMULA
Skov and Denver (1988) found the following formula
for ultimate pile capacity, Ru(t), as a function of relative
time between different tests
(1)
Some designations in this formula are different from
those given in the original expression. The pile capacity at the first
restrike, RRSTR-1, is the lower limit for appreciable
increasing in pile capacity when some time elapsed after initial driving
results in developing soil set-up. Quantity, t, is a time elapsed from
the end of initial driving and capacity RRSTR-1 is determined
for t=t1. A factor, A, is dependent on soil conditions.
Consolidation of cohesive soils around the pile after
pile installation requires much more time in comparison with other soil
types like sand and gravel to regain in soil strength and pile-soil
adhesion after EOID. For this reason the existing formula is pertinent
for clay and cohesive soils.
Case histories presented by Svinkin et al. (1994)
confirmed that formula (1) is a good indicator of the pile capacity
versus relative time relationship after pile installation. Besides, it
was shown that the factor, A, depends not only on the soil but also on
the pile type and size.
The application of formula (1) usually requires to
make the first restrike in 1-2 days after pile driving. It might be
especially convenient for dynamic testing at construction sites where
many piles should be tested by restrike in a short period of time.
Nevertheless, the existing formula yields relative
set-up versus relative time for assessment of the pile capacity after
the first restrike. This is a contradiction to the set-up approach
commonly used in geotechnical practice and inconvenient for certain
construction sites to restrike piles on 1-2 days after pile
installation.
3 PROPOSED FORMULA
The main goal to derive a new formula for evaluation
of the set-up effect of cohesive soils in pile capacity is to take into
consideration the pile capacity at EOID and the actual time elapsed
after pile installation.
For a soil set-up straight line passing through two
points corresponding pile capacity at EOID, REOID, and pile
capacity at any time after pile installation, Ru(t), a
formula with a logarithmic time scale can be written
(2)
Time is calculated in days after pile installation.
The time for EOID is taken 0.1 (2.4 hours) that negligibly affects
increasing in the pile capacity at EOID but gives an opportunity to use
the logarithmic time scale.
After simplification formula (2) becomes
(3)
Formula (3) is similar to formula (1). However,
proposed formula (3) has certain advantages. This formula (a) uses the
traditional set-up formulation, (b) takes into account the actual time
in days passed after pile installation, (c) provides determination of
the soil set-up independently of the time of the first restrike.
4 CASE HISTORIES
For verification of formula (3), in the following
case histories the existing and proposed expressions were used to
calculate the pile capacity as a function of time after EOID.
4.1 Case 1
Three piles were considered in this study from total
number of seven prestressed concrete piles tested for a bridge approach
(GRL Report 1987, Svinkin et al. 1994). A pile description is presented
in Table 1. The depth of penetration of each pile was approximately 24.4
m. The soil consisted of about 25.6 m of mainly gray clays followed by a
bearing layer of silty sand. Water table was at the ground surface. A
Delmag D 46-13 hammer was employed for initial driving and restrikes.
For each pile, 3 to 4 dynamic testings were performed after pile
installation. For piles TP3 and TP4 static loading tests (SLT) were made
as well. The elapsed time after EOID, the penetration resistance and the
time dependent ultimate capacity of piles tested are shown in Table 1.
Pile capacities from dynamic testings were determined by CAPWAP analysis
and the Davisson criterion of failure load was used for static loading
tests (GRL Manual 1993).
Pile capacity calculation according to formula (1)
was made by Svinkin et al. (1994). Quantity, t1, was equal to
2 days for piles TP1 and 1 day for piles TP3 and TP4. Measured data and
results calculated in accordance with the existing formula have been
plotted in ordinates Ru(t)/RRSTR-1 and log10(t/t1)
as broken and straight lines, respectively, in Figure 1. Note that
the set-up coefficients from the field tests generally match well to
those obtained from the existing formula.
|
Table 1. Static and Dynamic Data
for Prestressed Concrete and Steel Piles in Clayey Soils |
|
Pile |
Test |
Time after
EOID (days)
|
Penetration Resistance (blows/0.3 m)
|
Ru (kN)
|
Factor B
|
Set-up Measd
|
Set-up Calcd
|
|
No. |
Description |
|
TP1 |
1372 x 127 mm
Cylinder
Prestressed
Concrete |
EOID
RSTR-1
RSTR-2
RSTR-3 |
-
2
9
22 |
38
>240
>240
>240 |
752
2451
2927
3545 |
1.60 |
1
3.26
3.89
4.71 |
1
3.08
4.13
4.75 |
|
TP3 |
610 x 610 mm
(305 mm D. void)
Prestressed
Concrete
|
EOID
RSTR-1
RSTR-2
RSTR-3
SLT |
-
1
10
18
31 |
10
21
72
144
- |
267
912
1530
1672
1841 |
2.37 |
1
3.42
5.73
6.26
6.90 |
1
3.37
5.74
6.35
6.91 |
|
TP4 |
762 x 762 mm
(475 mm D. void)
Prestressed
Concrete
|
EOID
RSTR-1
RSTR-2
RSTR-3
RSTR-4
SLT |
-
1
4
9
18
32 |
14
23
60
>240
168
- |
200
890
1299
1517
1601
2273 |
3.50 |
1
4.45
6.50
7.60
8.00
11.37 |
1
4.45
6.61
7.84
8.90
9.77 |
|
B-2 |
HP 310x94
|
EOID
RSTR-1
RSTR-2
RSTR-3
SLT
RSTR-4
RSTR-5 |
-
2
6
7
15
16
132 |
12
36
60
72
-
48
>120 |
489
1201
-
1512
13972002
2291 |
1.14 |
1
2.46
-
3.09
2.86
4.09
4.69 |
1
2.48
-
3.10
3.48
3.50
4.55 |
- EOID - end of initial driving
|
|
|
- SLT - static loading test
|
For piles under consideration, the factor, B, has
been found on the basis of back calculations using formula (3). This
factor ranges from 1.6 to 3.5 (Table 1). Scattering of the factor, B, is
the same for the existing and proposed formulae. The set-up coefficients
derived from both the field tests and from formula (3) are given in
Table 1 and depicted in ordinates Ru(t)/REOID and
Time after EOID in days (logarithmic scale) as broken and straight
lines, respectively, in Figure 1. Good agreement is found between
calculated and measured values of pile capacity as a function of time
after EOID.

Figure 1. Pile capacity-time relationship for
prestressed concrete and steel piles in clayey soils
4.2 Case 2
Initial data for this case were taken after Fellenius
et al. (1989). An H-pile 310x94 (mm, kg/m) with length of 47.2 m was
driven and restruck by a Vulcan 010 hammer with a nominal energy of 44
kJ. Restrike No. 4 of this pile was performed by drop hammer with
nominal energy of 65 kJ. The soil at the site consisted of about 6.1 m
of miscellaneous earth fill followed by about 19.8 m of soft to medium
stiff compressible post-glacial silty clay and clayey silt underlain by
about 27.4 m of glacial material deposited on dolomite bedrock. The
water table was about 2.5 m below grade. The H-pile was founded in the
glacial material.
Five restrikes were made for pile tested. Pile
capacities from dynamic testings were determined by CAPWAP analysis (GRL
Manual 1993). The static loading test for this pile did not show a
plunging behavior. Failure load from the static loading test was 1397 kN
(Davisson 1972), 1957 kN (Butler & Hoy 1977), and 2535 kN (Fuller
& Hoy 1970). The capacity from the static loading test was evaluated
from the Davisson criterion. The results of dynamic and static tests are
shown in Table 1.
Pile capacity calculation according to formula (1)
was made by Svinkin et al. (1994) and shown in Figure 1. It can be seen
the calculated set-up line averages measured values of pile capacity.
Measured soil set-up and calculated set-up in
accordance with formula (3) are presented in Table 1 and displayed
in Figure 1 as well. For the H-pile, the proposed formula provides
better fit to results tested than the existing formula.
5 SUMMARY
The application of the proposed formula shows that
the magnitude of gain in pile capacity in cohesive soils depends on soil
conditions, pile material and dimensions. However, the same equation
with a different factor, B, can be applied for assessment of soil set-up
in cohesive soils during relatively long elapsed time after pile
installation.
The existing and proposed formulae demonstrate
similar tendency of the set-up effect of cohesive soil in pile capacity.
However, there are substantial differences between two approaches.
The existing formula yields relative set-up versus
relative time for assessment of the pile capacity after the first
restrike. This is a contradiction to the set-up approach commonly used
in geotechnical practice. Also, it is inconvenient for certain
construction sites to restrike piles on 1-2 days after pile
installation. Moreover there is no standard time for the first restrike.
If this time is different for various piles, the existing formula yields
different assessment of soil set-up at the same site and obtained
results of increasing in pile capacity cannot be compared.
The proposed formula uses the traditional set-up
formulation, calculates the pile capacity at the actual time after EOID,
and provides determination of the soil set-up independently of the time
of the first restrike.
The proposed formula provides determination of pile
capacity as a function of time after pile installation using pile
capacity values obtained through dynamic testing at EOID and one
restrike or one static loading test. This approach is identical for any
construction site. Obtained information would be beneficial to choose
sensible pile penetration depth at EOID and search the proper times in
days after EOID to verify set-up in cohesive soils with an additional
dynamic testing or the static loading test.
6 CONCLUSIONS
Determination of long term pile capacity is important
for proper design and construction of pile foundations in cohesive
soils.
A new relationship like a linear equation in a
logarithmic time scale has been derived to predict an increase in pile
capacity with time after pile installation. Soil set-up for several
piles in cohesive soils was verified on the basis of the existing and
proposed formulae. The latter has certain advantages. Obtained results
showed that changes of pile capacity with time in cohesive soil may be
predicted well.
Results presented in this paper certainly do not mean
that pile capacity will change with time exactly like shown above.
However, the demonstrated pile capacity versus time relationships can be
used as guide for assessment of pile capacity with respect to time.
Presented results give a chance to safe significant amount of time,
energy and materials taking into account the gain of pile capacity from
soil set-up. Derived relationship can also be useful in choosing
representative times for both static loading test and dynamic restrike
testing.
REFERENCES
- Butler, H.D. & H.E. Hoy 1977. Users manual for the Texas quick-load method for foundation load testing. FHWA, Office of Development, Washington.
|
- Davisson, M.T. 1972. High capacity piles. Proc., Lecture Series, Innovations in Foundation Construction, ASCE, Illinois Section.
|
- Fellenius, B.H., R.E. Riker, A.J. O'Brien, & G.R. Tracy 1989. Dynamic and static testing in soil exhibiting set-up. Journal of Geotechnical Engineering, 115(7): 984-1001.
|
- Fuller, R.M. & H.E. Hoy 1970. Pile load tests including quick -load test method, conventional methods and interpretations. HRB 333: 76-86.
|
- GRL and Associates, Inc. 1993. CAPWAP - Case Pile Wave Analysis Program, Manual, Cleveland, Ohio.
|
- GRL and Associates, Inc. 1987. Dynamic pile tests performed during June and July, 1987, Advance Pile Test Program, Louisiana DOT, Project No. 450-36-06, Cleveland, Ohio.
|
- Randolph, M.F., J.P. Carter & C.P. Wroth 1979. Driven piles in clay - the effect of installation and subsequent consolidation. Geotechnique, 29(4): 361-393.
|
- Skov, R. & H. Denver 1988. Time-dependence of bearing capacity of piles. In B. Fellenius (ed), Proc. Third Inter. Conf. on the Application of Stress-Wave Theory to Piles, Ottawa, 25-27 May: 879-888, Vancouver: BiTech Publisher.
|
- Seed, H.B. & L.C. Reese 1955. The action of soft clay along friction piles. Transactions, ASCE, 122: 731-754.
|
- Svinkin, M.R., C.M. Morgano & M. Morvant 1994. Pile capacity as a function of time in clayey and sandy soils. Proc. Fifth Inter. Conf. and Exhibition on Piling and Deep Foundations, Bruges, 13-15 June: 1.11.1-1.11.8, Rotterdam: Balkema.
|
- Thorburn, S. & W.J. Rigden 1980. A practical study of pile behavior. Proc. 12th Annual Offshore Technology Conf., Houston.
|
- Tomlinson, M.J. 1971. Some effects of pile driving on skin friction behavior of piles. Proc. Institution of Civil Engineers: 107-114, London.
|
- Wardle, I.F., G. Price & T.J. Freeman 1992. Effect of time and maintained load on the ultimate capacity of piles in stiff clay. Piling: European practice and worldwide trends, Proc. Institution of Civil Engineers: 92-99, London: Telford.
|
|