Mark R. Svinkin, Member, ASCE
VibraConsult
13821 Cedar Road, #205
Cleveland, OH 44118-2376
PH 216-397-9625
FAX 216-397-1175
msvinkin@vulcanhammer.net
Abstract
The application of dynamic methods to driven piles has
advantages in evaluation of the hammer-pile-soil system and in data
acquisition during pile driving and restrikes. Therefore during the last
twenty five years, dynamic methods have become an integral part of pile
capacity prediction and measurement for numerous projects. Dynamic
methods use good quality hardware and software, but such great tools
cannot themselves solve geotechnical problems of piling without
engineering judgment. This paper shows some engineering assessments of
determining pile capacity by dynamic formulas, wave equation analysis
and dynamic testing.
Introduction
Contemporary dynamic methods are founded on the
application of the stress wave theory to piles. There are two different
techniques of the use of wave equation analysis for determining pile
capacity: computation of pile capacity without dynamic measurements on
driven piles and a signal matching technique for computed and measured
force and velocity records at the pile head.
Dynamic methods have certain advantages and some
uncertainties in their application. The wave equation method is used for
prediction of pile capacity during both the design stage and for
construction control before restrikes. Unfortunately in most cases,
predicted pile capacity differs substantially from results of both
static and dynamic load tests. Dynamic measurements of force and
velocity at the upper end of the pile during pile driving, followed by a
signal matching procedure, is the most common method for dynamic
determination of pile capacity. This method is a convenient tool in the
pile driving industry. However, though dynamic methods have been used in
practice for years, actual accuracy of dynamic methods and understanding
the results of dynamic testing are vague.
Also, there is an attempt to breath new life into
dynamic formulas and consider a suggested formula as the better
alternative to signal matching technique. There are no theoretical and
experimental basis for such replacement.
In the medium of geotechnical engineers involved in
dynamic testing and analysis, there is a belief that hardware and
software themselves can solve geotechnical problems of piling. Indeed,
hardware and software are great tools but only tools, and these tools
cannot replace engineering judgment. It is known if we put trash in, we
will receive trash out. Computer misuse comes in many forms and among
them having computer programmers provide services they are unqualified
to perform. Formal implementation of the signal matching procedure is a
common approach in dynamic pile testing. In spite of a number of
excellent engineering assessment of results obtained from static and
dynamic tests, it is obvious that the application of dynamic methods to
piles lacks engineering judgment.
Misapplication and misuse of the specified computer
software are demonstrated. Various problems such as misleading
assessment of the accuracy of dynamic formulas, calibration of wave
equation programs, the soil consolidation effect in prediction of pile
capacity by wave equation analysis, comparison of static and dynamic
tests, prediction of pile capacity by dynamic pile testing,
overestimated capabilities of signal matching technique and others are
discussed. It is shown that dynamic methods have to be used with the
proper engineering judgment for prediction and determination of pile
capacity.
Dynamic Formulas
Determination of pile capacity by dynamic formulas is
the oldest and frequently used method. There is a great number of
dynamic formulas available with different degrees of reliability.
Dynamic formulas have been criticized in many publications.
Unsatisfactory prediction of pile capacity by dynamic formulas is well
characterized in FHWA Manual for Design and Construction of Driven Pile
Foundations, Hannigan et al.(1996): "Unfortunately, dynamic
formulas have fundamental weakness in that they do not adequately model
the dynamics of the hammer-pile impact, the influence of axial pile
stiffness, or soil response. Dynamic formulas have also proven
unreliable in determining pile capacity in many circumstances. Their
continued use is not recommended on significant projects".
However, dynamic formulas are traditional dynamic
analysis techniques. For example, responses to the questionnaire
obtained from 45 state DOTs and 2 FHWA officials showed that Dynamic
Formulas usage are 45% ENR (Engineering News Records) and 16%
Gates Equation, Paikowsky and Stenersen (2000). Besides, there is an
attempt to breathe new life into dynamic formulas. Paikowsky and
Chernauskas (1992), Paikowsky et al. (1994) and Paikowsky and Stenersen
(2000) have suggested one more energy approach using dynamic
measurements for the capacity evaluation of driven piles. Liang and Zhou
(1997) have concluded regarding this method: "Although the
delivered energy is much more exactly evaluated, this method still
suffers similar drawbacks of ENR".
Authors of a new dynamic formula used the ratio, also
called index K, of the static load test capacity to the predicted
capacity to evaluate performance of the energy approach and dynamic
testing. However, such a ratio is irrelevant for verification of dynamic
formulas and dynamic testing (DT) results for two reasons: first,
dynamic testing methods yield pile capacity only for the time of testing
(Rausche et al. 1985), and second, the pile capacity from static load
test (SLT) is considered as a constant value which is a major error.
Paikowsky et al. (1994) and Paikowsky and Stenersen
(2000) use a false assumption that accuracy of Dynamic Formulas are
independent of the time between DT and SLT. However, SLT as well as DT
yields the pile capacity at the time of testing (Svinkin 1997). By way
of illustration, results of DT and SLT are shown in Figure 1 for two
identical cylindrical, 1372 mm x 127 mm, prestressed concrete
piles, TP1 and TP2 (Svinkin et al. 1994). These piles were driven at the
same site to the depth of penetration of about 24.4 m. Each of the
piles TP1 and TP2 was tested 2, 9 and 22 days after the end of initial
driving (EOID). The difference was that three restrikes were made for
TP1 and three SLTs were made for TP2. Pile capacity from three SLTs was
a function of time as well as pile capacity obtained from DT. Tested
data in Figure 1 help to explain the causes of unsatisfactory prediction
in pile capacity by dynamic formulas. Dynamic formulas using maximum
energy, pile set and maximum displacement from DT do not take into
account the time between SLT and DT. In the case of a few SLTs made on
one pile, like three SLTs performed on pile TP2, what would be the
reliability of pile capacity prediction by the energy approach methods?
Which SLT should be taken for comparison? Currently, there are no
answers to these questions. Nevertheless, Paikowsky and Stenersen (2000)
assert that the Energy Approach Formula is ideal for construction and
better than Signal Matching technique, e.g. CAPWAP program (GRL
and Associates, Inc. 1995). There are no theoretical and experimental
confirmation of such conclusions which are wrong and misleading. It is
necessary to utilize other appropriate way for comparison of results of
the Energy Approach Formula and DT which use the same dynamic
measurements. Such comparison was made in the frames of preparation of
FHWA-GRL database. The results obtained were very poor and confirmed
that the Energy Approach with dynamic measurements cannot yield reliable
prediction of pile capacity. Statistical analysis itself cannot reveal
good results and replace engineering judgment if comparison of measured
pile capacities is incorrect.
Wave Equation Analysis
Limitations in Prediction of Pile Capacity
The main goal in using wave equation analysis is to provide a better prediction of the pile capacity, as a function of pile penetration resistance, than can be obtained from classical dynamic formulas. Today, the most commonly used wave equation programs are either GRLWEAP (GRL and Associates, Inc. 1997) or TNOWAVE (TNO Report 1996).
The wave equation method is used for prediction of pile
capacity prior to the beginning of pile driving and before restrikes.
However, in most cases, computed pile capacity differs substantially
from results of both static and dynamic load tests. Statistical analysis
of GRLWEAP results, Hannigan et al. (1996), computed for 99 piles driven
into various soils, has demonstrated that GRLWEAP does not have an
advantage over the Gates dynamic formula. The mean and coefficient of
variation are almost the same for both prediction methods.
Smith (1960) made his model on the basis of existing
knowledge of pile driving at the time and he supposed this model could
be improved with acquisition of new data. Results obtained by many
researchers confirmed that Smith's model is simple and sensible but with
some lack of proper presentation of soil properties.
Soil parameters considerably affect solutions of wave
equation analysis. Dynamic soil resistance parameters (damping and
quake) have to be assigned as constant values for wave equation
analysis. These parameters do not reflect the changes of soil properties
in the pile-soil interface zone after the completion of pile driving.
There have been attempts to determine values of damping
and quake from signal-matching solutions for dynamically tested driven
piles or from modified SPT. It could be beneficial for some cases, but,
in general, such approaches are not successful in finding proper values
of damping and quake. Besides complications with different models in
wave equation analysis and signal-matching technique and also with the
scale factor effect on the use of SPT results, these approaches yield
constant values of soil parameters and cannot be used in prediction of
the pile capacity as a function of time after EOID (Svinkin 1996).
Variable Soil Parameters.
Existing dynamic models of the pile-soil system mainly use a velocity-dependent approach for calculation of the dynamic resistance as a damping component of the total resistance during pile driving. There are various linear and nonlinear relationships between the damping component and the velocity. A study of different soil damping models and computed pile capacities has revealed that neither the pile velocity nor the damping constant can reflect time-dependent variation of the pile-soil system after EOID. The existing approach of computing the dynamic resistance does not take into account soil consolidation around the pile after EOID and therefore cannot provide determination of pile capacity as a function of time after pile installation. There is necessity to take into account soil consolidation around a pile after EOID for improvement in accuracy of wave equation analysis, Svinkin (1996).
For the idealized Smith wave equation model, it is important to find an appropriate combination of parameter values, mainly paying attention to soil variables, in order to achieve the accurate prediction of pile capacity. There is a reasonable way to enhancing prediction accuracy of the dynamic resistance with the velocity dependent approach. Variation of the pile-soil system after the completion of driving can be taken into account by a variable damping coefficient which should be considered as a function of time and other parameters characterizing soil consolidation around the pile, Svinkin (1996, 1997). It is assumed that the variable damping coefficient is independent of pile velocity. Inclusion of variable damping is thought to be the next step in the development of Smith's model with the velocity dependent approach for representation of the dynamic resistance.
The damping coefficient as a function of time can be
found on the basis of back calculations using the wave equation model of
the pile-soil system with known capacity as This procedure is in
agreement with Lambe's (1973) equation modified for a general back
analysis approach by Leroueil & Tavenas (1981). Since the variable
damping coefficient is chosen as only one soil parameter reflecting the
field soil consolidation after pile installation, this parameter can be
successfully back analyzed.

The results of back analysis has revealed that the shaft damping
coefficient in clay is much higher than in unsaturated sand, but upper
values of this coefficient in saturated sandy soil (sand with high
damping) are close to ones in clay, Svinkin and Woods (1998). Also, a
trend of the damping coefficient increase with time after EOID was found
for all soil damping models available in GRLWEAP program and this trend
is independent of the damping resistances, Svinkin (1996).
The idea of variable damping has been confirmed by results of
statistical analysis of damping coefficients from CAPWAP solutions
performed by Liang and Zhou (1997) who have found that the damping
coefficient is affected by the time. Cho et al. (2000) agree that set-up
effects should be accounted for in wave equation analysis for restrikes
and suggested constant damping and quake coefficients to computing pile
capacity before restrike. This is a partial solution because these
coefficients can be used only for one restrike. The variable damping
coefficient is a solution for calculation of pile capacity before
different restrikes.
Soil
damping is the key parameter for adjustment of wave equation solutions
with time-dependent soil properties in pre-driving analysis. The use of
the variable damping coefficient gives an opportunity to compute the
time-dependent pile capacity by the wave equation method.
Software Calibration.
Existing programs for wave equation analysis are not the same. Moreover all
programs have a number of versions. Each new version gives usually
additional beneficial options to users, but it is not clear how each
program version ensures the accuracy of pile capacity calculation. There
is confusion what program yields more accurate results. The writer has
an experience of pile capacity calculation for the same hammer, pile and
soil conditions using two versions of the same program. Variation of
obtained capacities was about 20 %. This is an evidence of
contradictions available between different program versions.
Obviously,
it is necessary to calibrate each program version with some standard
data of the hammer-pile-soil system in order to avoid confusion in a
choice of the program.
Dynamic
Testing
Dynamic
testing followed by a signal matching procedure has obvious advantages
in determining pile capacity at any time required after pile
installation. Since dynamic testing is often used to replace the static
loading tests, it is important to ascertain the adequacy of both SLT and
DT.
Existing
Approach for Comparison of SLT and DT.
Static analysis methods predict pile capacity as the long term
capacity after soil consolidation around the pile is complete.
Independently of the time elapsed between installation of the
test pile and the static loading test, the ratio of the predicted
ultimate load to the measured ultimate load from static loading test is
used for approximate evaluation of the reliability of design methods.
For example, Briaud and Tucker (1988) evaluated 13 methods developed to
predict the ultimate load capacity of the pile, and they used this ratio
for approximate evaluation of the reliability of design methods in
calculation of the ultimate pile load although the time elapsed between
installation of the test pile and static load test averaged 17 days.
According
to the traditional approach, the main criterion for assessment of the
pile capacity prediction based on dynamic measurements is the ratio of
capacities obtained by dynamic and static tests or vice versa (Figure
2). It is necessary to point out that a ratio of DT/SLT or vice versa,
taken for arbitrary time between compared tests, is not a verification
of dynamic testing results. It is well-known that dynamic testing
methods yield the real static capacity of piles at the time of testing,
Rausche et al. (1985). Besides, the static capacity from SLT is
considered as a unique standard for assessment of dynamic testing
results. Unfortunately, that is a major error.
As a matter of fact, pile capacity from Static Loading Tests is a
function of time and the so-called actual static capacity from SLT is
not a constant value, Svinkin (1997; 1998).
For
the general case of assessment of reliability of the DT, the ratio of
restrikes to SLT results has been considered for various pile types,
soil conditions and times of testing lumped together as shown in Figure
2. Such mixture has no real meaning. It is not a verification of dynamic
testing at restrikes and it is not an assessment of real set-up factor
because everything is lumped together without taking into account the
time between different tests. Such a comparison of the pile capacities
from SLT and DT is invalid for piles driven in soils with time-dependent
properties because the soil properties at the time of DT do not
correspond to the soil properties at the time of SLT i.e. soil
consolidation is taken into account for the latter test and not
considered for the former test. As a matter of fact, such a comparison
uses pile capacity values which are incompatible from the point of DT
verification, Svinkin (1997) and Svinkin and Woods (1998).
New Criteria for Comparison of SLT and DT. Criteria should be established for correct comparison of in-situ tests made at different times after EOID. It is important to find how changes of pile capacity between two compared tests may affect the accuracy of determining pile capacity by dynamic testing.
Acceptable time between tests. Pile capacity determined at EOID in various soils changes with time. After the completion of pile driving, soil consolidation, manifested by the dissipation of excess pore pressure at the soil-pile interface zone, is usually accompanied by an increase in pile capacity (soil set-up). In saturated sandy soils, ultimate pile capacity may decrease (soil relaxation) after initial driving due to dissipation of negative pore pressure. Changes of strength in soil after driving and the time required for return of equilibrium conditions are highly variable and depend on soil conditions, and pile type and size. The consequences of soil modification around the pile are essential with respect to changes of pile capacity. Pile capacity as a function of time is displayed, for example, in Figure 1 for piles TP1 and TP2. Comparison of values of the pile capacity obtained from two tests with arbitrary time between them show only a change of pile capacity during a considered period of the time, but it is not verification of DT.

Static
Loading Tests and Dynamic Testing present different ways of determining
pile capacity at various times after pile installation, but for valid
correlations of both tests, static and dynamic testing capacities must
be compared at the same time after pile installation in both SLT and DT
methods, Svinkin (1997; 2000) and Svinkin and Woods (1998).
The
adequacy of SLT and DT have to be confirmed by proper correlation of
time. Due to the
consolidation phenomenon in soils, comparison of SLT and DT can be made
only for tests performed immediately one after another.
In practice, it is sometimes difficult to make two immediately
successive tests, but nonetheless the time difference between both
comparable tests should not exceed 1-2 days during which soil setup
changes only slightly.
Rate of pile capacity change. It is important to find quantitative assessment of pile capacity change during 1-2 days. The rate of pile capacity change per day (set-up rate), rR, between two
considered tests can be calculated as

Where
Ru1 = pile capacity from test 1; Ru2 = pile
capacity from test 2; t1 and t2 = elapsed time in
days after EOID for test 1 and test 2, respectively.
The set-up rate was calculated for different pile types tested in
various soils. Pile
capacity from dynamic testings was determined by CAPWAP analysis and the
Davisson criterion of failure load was used for static loading tests,
Davisson (1972). The obtained results are shown in Table 1-3. Initial
data for these tables were taken from Svinkin et al. (1994).
A description of seven prestressed concrete piles is presented in
Table 1. The depth of penetration of each pile was approximately 24.4 m.
The soil consisted of about 25.6 m of mainly gray clays followed by a
bearing layer of silty sand. Water table was at the ground surface. A
Delmag D 46-13 hammer was employed for initial driving and restrikes (RSTR).
For each pile, 3 to 4 DT and/or SLT were performed after pile
installation. The elapsed time after EOID, penetration resistance and
the time dependent ultimate capacity of tested piles are shown in
Table 1 as well. It can be seen that the set-up rate depends on the
elapsed time after pile installation. The set-up rate was about few
hundred in 1-2 days after pile installation. Then the rate considerably
decreased and became 13-16 %/day for four days after EOID and less than
7-8 %/day for 9-10 days after EOID, Figure 3.
|
Table 1. Static and Dynamic Data for Prestressed Concrete Piles in Clay over Silty Sand
|
|
Pile
|
Test
|
Time
after
EOID
(days)
|
Penetration
Resistance
(blows/0.3 m)
|
Ru
(kN)
|
Set-up
Measd
|
Set-up
Rate
(%/day)
|
|
No.
|
Description
|
|
|
|
|
|
|
|
TP1
|
1372 mm x 127 mm
Cylinder
|
EOID
RSTR-1
RSTR-2
RSTR-3
|
-
2
9
22
|
38
>240
>240
>240
|
752
2451
2927
3545
|
1
3.26
3.89
4.71
|
-
113
3
2
|
|
TP2
|
1372 mm x 127 mm
Cylinder
|
EOID
SLT-1
SLT-2
SLT-3
|
-
2
9
22
|
48
-
-
-
|
712
1913
2789
3189
|
1
2.69
3.92
4.48
|
-
84
7
1
|
|
TP3
|
610 mm x 610 mm
(305 mm D. void)
|
EOID
RSTR-1
RSTR-2
RSTR-3
SLT
|
-
1
10
18
31
|
10
21
72
144
-
|
267
912
1530
1672
1841
|
1
3.42
5.73
6.26
6.90
|
-
242
8
1
<1
|
|
TP4
|
762 mm x 762 mm
(475 mm D. void)
|
EOID
RSTR-1
RSTR-2
RSTR-3
RSTR-4
SLT
|
-
1
4
9
18
32
|
14
23
60
>240
168
-
|
200
890
1299
1517
1601
2273
|
1
4.45
6.50
7.60
8.00
11.37
|
-
345
15
3
<1
3
|
|
TP5
|
762 mm x 762 mm
(475 mm D. void)
|
EOID
RSTR-1
RSTR-2
RSTR-3
RSTR-4
SLT
|
-
1
4
11
20
34
|
23
59
96
91
>240
-
|
262
952
1401
1588
1748
2473
|
1
3.63
5.37
6.06
6.67
9.44
|
-
263
16
2
1
3
|
|
TP6
|
914 mm x 127 mm
Cylinder
|
EOID
RSTR-1
RSTR-2
RSTR-3
RSTR-4
SLT
|
-
1
4
11
21
35
|
15
34
64
162
113
-
|
400
885
1241
1766
2300
2406
|
1
2.21
3.10
4.42
5.75
6.02
|
-
121
13
6
3
<1
|
|
TP7
|
914 mm x 127 mm
Cylinder (spliced)
|
EOID
RSTR-1
RSTR-2
RSTR-3
RSTR-4
SLT
|
-
1
4
10
20
35
|
32
32
102
168
186
-
|
454
876
1285
1890
2260
2406
|
1
1.93
2.83
4.16
4.98
5.30
|
-
93
16
8
2
<1
|
|
Table 2. Static and Dynamic Data for Piles in Unsaturated Sandy Soils
|
|
Pile
|
Test
|
Time
after
EOID
(days)
|
Penetration
Resistance
(blows/0.3 m)
|
Ru
(kN)
|
Set-up
Measd
|
Set-up
Rate
(%/day)
|
|
No.
|
Description
|
Embdt
(m)
|
|
|
|
|
|
|
|
1
|
Prestressed concrete
508 mm x 508 mm
(38 mm D. void)
|
38.0
|
EOID
RSTR-1
SLT
|
-
3
12
|
110
1114
-
|
2487
3243
6450
|
1
1.30
2.59
|
-
10
11
|
|
2
|
Prestressed concrete
356 mm x 356 mm
|
27.4
|
EOID
RSTR-1
SLT
|
-
7
16
|
68
78
-
|
1134
2309
3736
|
1
2.03
3.29
|
-
15
7
|
|
3
|
324 mm O.D. by 6 mm thick closed end steel pipe
|
25.3
|
EOID
RSTR-1
SLT
|
-
7
14
|
27
48
-
|
681
1232
2224
|
1
1.81
3.26
|
-
12
12
|
|
Table 3. Static and Dynamic Data for Prestressed Concrete Piles in Saturated Sandy Soils
|
|
Pile
|
Test
|
Time
after
EOID
(days)
|
Penetration
Resistance
(blows/0.3 m)
|
Ru
(kN)
|
Set-up
Measd
|
Set-up
Rate
(%/day)
|
|
No.
|
Description
|
Embdt
(m)
|
|
|
|
|
|
|
|
CT1
|
457 mm x 457 mm
|
19.7
|
EOID
RSTR-1
RSTR-2
SLT
|
-
2
11
21
|
18
84
84
-
|
913
1145
1702
1666
|
1
1.25
1.86
1.85
|
-
13
5
-<1
|
|
CT2
|
457 mm x 457 mm
|
22.9
|
EOID
RSTR-1
RSTR-2
SLT
|
-
2
11
21
|
42
84
60
-
|
1907
2176
2668
2540
|
1
1.14
1.40
1.34
|
-
7
4
-<1
|
|
CT3
|
610 mm x 610 mm
(267 mm D. void,
solid ends)
|
19.5
|
EOID
RSTR-1
RSTR-2
SLT
|
-
1
10
22
|
34
72
108
-
|
1513
-
2615
2869
|
1
-
1.73
1.90
|
-
-
7
<1
|
|
CT4
|
610 mm x 610 mm
(267 mm D. void,
solid ends)
|
22.9
|
EOID
RSTR-1
RSTR-2
SLT
|
-
2
11
23
|
77
96
216
-
|
1986
2691
3617
3724
|
1
1.35
1.82
1.90
|
-
18
4
<1
|
|
CT5
|
915 mm x 915 mm
(570 mm D. void,
solid ends)
|
22.3
|
EOID
RSTR-1
SLT
|
-
6
20
|
92
60
-
|
2949
4210
4900
|
1
1.43
1.66
|
-
7
1
|
Three piles, two prestressed concrete and one closed
ended steel pipe, are presented in Table 2. These piles were tested at
different sites but their soil conditions were very close: predominantly
unsaturated sandy soils. Soil deposits were mostly fine sands with bare
strata of silty sand at site 1 and slightly silty or clayey fine sands
at sites 2 and 3. The water table was not encountered during soil boring
on each site. For pile 1, a Kobe K-45 hammer was used. Piles 2 and 3
were driven and restruck with a Vulcan 80C and 010 hammers,
respectively. For unsaturated sands, the set-up rate was mostly
independent of the limited elapsed time of 12-16 days after pile
installation and was found in the range of 10-15 %/day.
Five prestressed concrete piles were driven on a site
with predominantly silty sands (Table 3). The water table was at a
depth of 0.6 m from ground surface. Piles CT1, CT2, CT3, and CT4 were
driven and restruck with a Kobe K25 hammer. A Delmag D 62-22 hammer was
used for pile CT5. The set-up rate was 7-18 %/day, 4-7 %/day, and less
than 1 %/day for 2, 10-11, and 20-23 days after EOID.
Thus, the rate of pile capacity change per day, rR,
decreases with an increase of the elapsed time after EOID and a margin
of error about 10-15 %/day would be reasonable for a few days after pile
installation.
Comparison of SLT and DT. Thirty nine different piles in various soil conditions were statically and dynamically tested (Table 4). Initial data for these piles were taken from FHWA-GRL database.
Explanation of abbreviations in Table 4 are as follows.
Pile number: number in parentheses is from FHWA Database; Pile
description: PSC is prestressed concrete, OEP is open ended pipe, CEP is
closed ended pipe, HP is H-pile; Soil: HWT is high water table; Time
between SLT & DT: minus and plus mean DT was made before or after
SLT, respectively; Time after EOID was shown for DT; Signal Matching:
reanalyzed results include the "automatic" or "best
match" (with asterisk), minus and plus in error mean under or
overestimated CAPWAP results.
Static load tests were carried to failure according to
the Davisson failure criterion. Dynamic records from restrike testing
were available for all piles. A signal matching technique - CAPWAP
analysis of the restrike test data was used for pile capacity
determination. The "original" CAPWAP capacities were obtained
from existing CAPWAP results. For a number of piles, additional CAPWAP
analysis was provided because of absence of the "original"
CAPWAP capacities or in order to improve signal matching results with
"automatic" or "best match" solutions.
"Automatic" is an option in the CAPWAP program with automatic
search capability which provides a solution using optimal matching of
signals with no user interaction. "Best match" is a result of
working in a manual operating mode to iteratively seek a best match.
For all considered piles, the time differences between
static and dynamic tests were 1-2 days, but time elapsed after EOID was
diverse. An acceptable margin of error was determined in accordance with
the set-up rate in Tables 1-3. Compared capacities have a good agreement
within the acceptable margin of error for 28 piles (1, 3, 4, 5, 6, 8, 9,
11, 13, 15, 16, 17, 19, ,20, 21, 22, 24, 25, 26, 27, 28, 30, 31, 32, 34,
37, 38, 39). Piles with at least one CAPWAP result within the acceptable
limits were included in this group. For example, for pile 11
"original" and "automatic" CAPWAP yielded the pile
capacity with an error of -8 % and -40 %, respectively, but even
the big error is acceptable in this case because the elapsed time after
EOID was only 1 day and DT was made 2 days before SLT. Calculated
capacities for five piles (12, 14, 18, 29, 33) have errors from 20 % to
25 %. The worst results were obtained in CAPWAP analysis of six piles
(2, 7, 10, 23, 35, and 36) which were analyzed with errors between 30-54
%. First three piles have underestimated results, but piles 23, 35 and
36 have overestimated pile capacity on 31 %, 54 % and 44 %,
respectively.
Table 4. Comparison of pile capacities obtained from SLT
and DT
Pile
|
Soil
|
SLT
|
Time
between
|
Dynamic Testing
|
Signal Matching
|
|
No.
|
Description
|
Length
(m)
|
|
(kN)
|
SLT & DT
(hours)
|
Time
a/EOID
(days)
|
Test
|
Blow
Count
(bl/0.3 m)
|
Original
(kN)
|
Error
(%)
|
Reanalzd
(kN)
|
Error
(%)
|
|
1(1)
|
610 mm PSC
305 mm void D.
|
28.42
|
Sand
HWT
|
4228
|
+24
|
13
|
RSTR-2
|
360
|
4116
|
-2.6
|
3498*
|
-17
|
|
2(3)
|
610 mm PSC
305 mm void D.
|
20.20
|
Sand & Clay
HWT
|
3160
|
+24
|
12
|
RSTR-2
|
240
|
2011
|
-36
|
2216
|
-30
|
|
3(5)
|
610 mm PSC
305 mm void D.
|
24.54
|
Sand & Clay
HWT
|
3560
|
+24
|
24
|
RSRT-2
|
288
|
3573
|
+0.4
|
-
|
-
|
|
4(6)
|
610 mm PSC
305 mm void D.
|
37.69
|
Clay & Sand
HWT
|
3560
|
+24
|
24
|
RSTR-2
|
720
|
3467
|
-2.6
|
4041*
|
+14
|
|
5(7)
|
610 mm PSC
305 mm void D.
|
37.03
|
Sand & Clay
HWT
|
4361
|
+24
|
29
|
RSTR-2
|
576
|
3386
|
-22
|
4236*
|
-3
|
|
6(46)
|
610 mm PSC
|
25.58
|
Sand, HWT
|
2216
|
+24
|
13
|
RSTR-2
|
120
|
2114
|
-4.6
|
2123
|
-4.2
|
|
7(48)
|
762 mm PSC
457 mm void D.
|
31.10
|
Sand
HWT
|
6635
|
+48
|
31
|
RSTR-2
|
432
|
3039
|
-54
|
3836*
|
-42
|
|
8(49)
|
762 mm PSC
457 mm void D.
|
30.80
|
Sand & Clay
HWT
|
2812
|
+24
|
10
|
RSTR-2
|
144
|
2523
|
-10
|
2376
|
-16
|
|
9(50)
|
762 mm PSC
457 mm void D.
|
31.57
|
Sand & Clay
HWT
|
4005
|
+24
|
33
|
RSTR-2
|
312
|
-
|
-
|
3435*
|
-14
|
|
10(51)
|
762 mm PSC
457 mm void D.
|
30.02
|
Sand, HWT
|
6439
|
+24
|
26
|
RSTR-2
|
264
|
-
|
-
|
3751*
|
-42
|
|
11(56)
|
610 mm PSC
76 mm void D.
|
19.60
|
Sand with Silt
& Clay, HWT
|
3524
|
-48
|
1
|
RSTR-1
|
72
|
3253
|
-8
|
2100
|
-40
|
|
12(62)
|
610 mm PSC
|
58.52
|
Sand, Clay HWT
|
2893
|
+24
|
8
|
RSTR-2
|
80
|
2382
|
-17
|
2203
|
-24
|
|
13(68)
|
610 mm PSC
102 mm void D.
|
27.43
|
Clay & Sand
HWT
|
4717
|
+48
|
21
|
RSTR-1
|
1000
|
4517
|
-4.2
|
4632
|
-1.8
|
Table 4. continued. Comparison of pile capacities
obtained from SLT and DT
Pile
|
Soil
|
SLT
|
Time
between
|
Dynamic Testing
|
Signal Matching
|
|
No. |
Description
|
Length
(m)
|
|
(kN)
|
SLT & DT
(hours)
|
Time
a/EOID
(days)
|
Test
|
Blow
Count
(bl/0.3 m)
|
Original
(kN)
|
Error
(%)
|
Reanalzd
(kN)
|
Error
(%)
|
|
14(69)
|
406 mm PSC
102 mm void D.
|
24.38
|
Clay & Sand
HWT
|
2626
|
+48
|
15
|
RSTR-1
|
180
|
3204
|
+22
|
-
|
-
|
|
15(70)
|
HP 346x109
|
27.43
|
Clay, HWT
|
2750
|
+48
|
34
|
RSTR-1
|
1000
|
2799
|
+1.7
|
-
|
-
|
|
16(71)
|
HP 346x109 |
27.43
|
Sand & Clay
HWT
|
1393
|
+24
|
10
|
RSRT-1
|
96
|
-
|
-
|
1517*
|
+8.9
|
|
17(72)
|
610 mm x 13 mm
OEP
|
25.91
|
- |
2670
|
+24
|
10
|
RSTR-1
|
150
|
-
|
-
|
2652*
|
-0.7
|
|
18(73)
|
610 mm PSC
Octagonal
|
25.91
|
Sand & Clay
HWT
|
4873
|
+24
|
10
|
RSTR-1
|
1000
|
3783
|
-22
|
3814
|
-22
|
|
19(74)
|
305 mm PSC
|
27.74
|
Sand, Clay
& Silt, HWT
|
1602
|
+48
|
22
|
RSTR-3
|
208
|
-
|
-
|
1687*
|
+5
|
|
20(75)
|
610 mm PSC |
24.84
|
Sand & Clay
HWT
|
2238
|
+24
|
3
|
RSTR-1
|
24
|
2448
|
+9
|
2617
|
+17
|
|
21(76)
|
610 mm PSC |
20.27
|
Sand & Clay
HWT
|
4650
|
+24
|
3
|
RSTR-1
|
60
|
-
|
-
|
5006*
|
+7.6
|
|
22(92)
|
244 mm x 14 mm
CEP
|
44.20
|
Sand & Clay |
2924
|
+48
|
52
|
RSTR-2
|
602
|
2559
|
-12.4
|
2051
|
-43
|
|
23(102)
|
HP 299x79 |
22.86
|
-
|
1664
|
+5
|
1
|
RSTR-2
|
192
|
2185
|
+31
|
-
|
-
|
|
24(103)
|
HP 299x79 |
12.19
|
- |
2318
|
+5
|
1
|
RSTR-1
|
360
|
2323
|
+0.2
|
-
|
-
|
|
25(104)
|
HP 299x79
|
24.38
|
-
|
1682
|
+5
|
1
|
RSTR-1
|
240
|
1918
|
+14
|
-
|
-
|
|
26(121)
|
406 mm x 6 mm
CEP
|
12.10
|
Sand & Silt |
1161
|
+24
|
10
|
RSTR-1
|
107
|
1077
|
-7
|
1068
|
-8
|
Table 4. continued. Comparison of pile capacities
obtained from SLT and DT
Pile
|
Soil
|
SLT
|
Time
between
|
Dynamic Testing
|
Signal Matching
|
|
No.
|
Description
|
Length
(m)
|
|
(kN)
|
SLT & DT
(hours)
|
Time
a/EOID
(days)
|
Test
|
Blow
Count
(bl/0.3 m)
|
Original
(kN)
|
Error
(%)
|
Reanalzd
(kN)
|
Error
(%)
|
|
27(122)
|
800 mm PSC
560 mm void D.
|
18.00
|
Clay & Sand
HWT
|
659
|
+24
|
10
|
RSTR-1
|
46
|
-
|
-
|
699*
|
+9
|
|
28(129)
|
387 mm/140 mm
Timber
|
10.67
|
Clay, Loam, Till
|
757
|
+2
|
<1
|
RSTR-1
|
60
|
659
|
-13
|
636
|
-16
|
|
29(130)
|
324 mm x 6 mm
CEP
|
24.99
|
Silt
|
970
|
+24
|
16
|
RSRT-1
|
120
|
797
|
-18
|
774
|
-20
|
|
30(133)
|
(356 mm x 5 mm)
(318 mm x 6 mm)
(279 mm x 6 mm)
CEP
|
24.08
|
Silt & Clay
|
1197
|
+24
|
26
|
RSTR-1
|
600
|
1046
|
-13
|
-
|
-
|
|
31(154)
|
457 mm PSC
|
13.72
|
Sand, HWT
|
1041
|
+48
|
6
|
RSTR-1
|
42
|
730
|
-30
|
948
|
-9
|
|
32(155)
|
457 mm PSC
|
10.67
|
Sand
|
757
|
+24
|
4
|
RSTR-1
|
34
|
-
|
-
|
730*
|
-3.5
|
|
33(165)
|
324 mm x 13 mm
CEP
|
27.43
|
Clay & Silt
HWT
|
2496
|
+12
|
17
|
RSTR-1
|
96
|
3115
|
+25
|
-
|
-
|
|
34(166)
|
324 mm x 13 mm
CEP
|
27.43
|
Clay & Silt
HWT
|
2211
|
+24
|
17
|
RSTR-1
|
72
|
2390
|
+8
|
-
|
-
|
|
35(169)
|
324 mm x 13 mm
CEP
|
21.00
|
-
|
788
|
-24
|
14
|
RSTR-1
|
48
|
1504
|
+54
|
-
|
-
|
|
36(170)
|
324 mm x 13 mm
CEP
|
17.00
|
-
|
712
|
-24
|
14
|
RSTR-1
|
24
|
1148
|
+44
|
-
|
-
|
|
37(183)
|
305 mm PSC
|
26.52
|
Sand & Silt
|
1691
|
+24
|
12
|
RSTR-3
|
Refusal
|
1927
|
+14
|
-
|
-
|
|
38(184)
|
305 mm PSC
|
24.08
|
Sand & Silt
|
1090
|
+24
|
16
|
RSTR-3
|
120
|
1144
|
+5
|
-
|
-
|
|
39(185)
|
244 mm x 19 mm
OEP
|
43.61
|
Clay with Silt
& Sand
|
1896
|
-24
|
2
|
RSTR-1
|
60
|
1900
|
0
|
1878
|
<1
|
Comments about the worst obtained results. Pile 2 was tested at the same site with piles 1, 3, 4, and 5, but only pile 2 has a big error. "Automatic" analysis decreased an error from -36 % to -30 %. Perhaps the quality of the velocity record is the reason of unsatisfactory solution. Dynamic testing records of piles 2 and 4 (for comparison) are depicted in Figure 4. For pile 7,
"automatic" analysis decreased an error in calculation of pile
capacity from -54 % to -42 %. The time between SLT and DT was 2 days,
but an elapsed time after EOID was 31 days. For such period of time the
difference between compared tests should be minimal. There is no obvious
explanation of the underestimating pile capacity for pile 7. An error in
the computed capacity of pile 10 was -42 % in spite of the
"best match" solution. Relaxation of pile capacity is possible
in saturated sand, but 42 % of decreasing pile capacity on the 26th day
after EOID and 1 day after SLT is very strange. For pile 23, the
computed pile capacity with an error of +31 % is acceptable because the
elapsed time after EOID was 1 day. Overestimating capacities for piles
35 and 36 were computed with big errors of +54 % and +44 %,
respectively. These results may be explained with implementation of DT
on one day before SLT.
It can be seen the computed capacities for 11 piles
exceeded a reasonable margin of error. The Davisson criterion determines
a conservative value of pile capacity. Maximum values of pile capacity
can be estimated with the Chin method from which results are about 20 %
to 40 % greater than from the Davisson limit, Fellenius (2001).
Therefore, computed pile capacity exceeding the Davisson limit more than
20 % should be considered as overestimating values. It is not acceptable
for pile foundation design. Underestimating pile capacities are good for
foundation safety but not acceptable from the economic standpoint.
Analysis of 39 cases revealed substantial errors in determination of the
pile capacity for 6 piles that is about 15 % of the total number of
considered piles. However, it is important to recognize such cases.
Besides formal implementation of signal matching procedure, it is
necessary to use engineering judgment in assessment of DT results. The
main objective of this study is to bring attention of geotechnical
engineers to engineering judgment of dynamic testing in order to
recognize bad situations in advance.
Effects of various factors on Results of DT. It
is important to reveal how various factors affect signal matching
results.
Time between compared tests was in the limits of 1-2 days. The time was 48 hours for 8 piles, 24 hours for 26 piles, 12 hours for 1 pile, 5 hours for 3 piles, and 2 hours for 1 pile. Thus, closely time correlated comparisons of SLT and DT have been made.
Time after pile installation affects the rate of pile capacity change. This rate is different for various soils, but a margin of error about 10-15 %/day would be reasonable for a few days after pile installation. For short period after EOID, larger discrepancies are acceptable as was shown for pile 11 and in Figure 3.
Sequence of tests. Four piles (11, 35, 36, and 39) were dynamically tested before SLT. Piles 11 and 39 were tested on the first and the second days, respectively, after EOID when soil consolidation only started and the difference between pile capacities from DT and SLT was acceptable. Piles 35 and 36 were tested on the 14th day. DT destroyed soil consolidation around the pile and during one day soil could not reconsolidate. Perhaps this is the cause of the big discrepancy between compared pile capacities. Therefore, DT should be made after SLT to obtain better results.
Pile type. No correlations was found between pile type and pile capacities computed.
High blow count. No correlations was found between high blow count and pile capacities computed.
Signal matching technique. "Automatic" signal matching improved results computed for 8 piles (2, 6, 13, 18, 22, 26, 31, 39) and made worse calculations for 6 piles (8, 11, 12, 20, 28, 29). "Best match" changed for the worse the pile capacity of only pile 1. It is obvious that "best match" is preferred procedure in signal matching technique. Described results were obtained with CAPWAP program, but similar outputs could be expected from the use of TNODLT program, TNO Report (1996).
Dynamic records should affect computed result. One example was shown in the text. There is a trend to improve wrong records by means of signal matching technique, but it is unknown how record improvement affects computing pile capacity. It seems to be beneficial to prepare a catalog of unacceptable records.
Soil conditions. It is necessary to collect more information in order to reveal effects of soil conditions on computed results.
Prediction of Pile Capacity by DT. Obviously, at
EOID and each restrike the pile-soil system has various soil stiffness,
damping and soil mass involved in vibration. Therefore, each dynamic
testing yields pile capacity corresponding to the properties of the
pile-soil system at the time of testing. The pile capacity from a static
load test reflects a degree of soil consolidation around a pile at the
time of testing as well. Thus, static, dynamic and statnamic tests
determine pile capacity only at the time of testing.
In some publications, dynamic testing is used for a capacity prediction without prior knowledge of the static loading test, e.g. Goble (2000) and Holeyman et al. (2000). This is a misleading interpretation of DT which does not have any connection with Class A type prediction defined by Lambe (1973). No in-situ pile test can predict pile capacity as a function of time after pile installation.
Overestimated software capabilities. It is
sometimes difficult to activate the pile capacity at restrike and
software users calculate the undetermined pile capacity with combined
CAPWAP analysis, Stevens (2000). The pile capacity is estimated by
compounding resistance distribution from two different DT and using the
highest values between the two for each soil element. It seems that such
a procedure overestimates capabilities of signal matching technique. It
is important to verify similar calculations with SLT or use the special
driving technique (Fellenius 1999) which means that one of the nearby
piles is driven at EOID shorter so that there is confidence that at
restrike the pile will move and its full resistance will be mobilized.
The nearby not mobilized piles can be said to have the same shaft
resistance and at least as much toe resistance.
Conclusions
The paper's objective is an attempt to emphasize the
engineering judgment and eliminate contradictions and/or
misunderstanding of determining pile capacity by dynamic methods. The
paper demonstrates misapplication and misuse of the specified computer
software. It is shown the necessity of consideration of the soil
consolidation effect in prediction of long-term pile capacity by wave
equation analysis, calibration of wave equation programs, and proper
comparison of static and dynamic tests. Also, it is underlined
impossibility to predict pile capacity by dynamic pile testing,
misleading assessment of the accuracy of dynamic formulas, and paid
attention to overestimated capabilities of signal matching technique.
Dynamic methods have to be used with the proper engineering judgment for
prediction and determination of pile capacity.
Acknowledgement
The writer is grateful to the Federal Highway
Administration (FHWA) and GRL and Associates, Inc. for assistance in the
use of FHWA-GRL database. Opinions expressed in this paper are those of
the writer and not necessarily those of FHWA and GRL and Associates,
Inc. The writer wishes to thank the reviewers for their constructive
reviews of the paper.
APPENDIX I.REFERENCES
Briaud, J.L. Tucker, L.M. (1988). "Measured and predicted axial response of 98 piles", Journal of Geotechnical Engineering, ASCE, 114(9), 984-1001.
Cho, C.W., Lee, M.W., and Randolph, M.F. (2000). "Set-up considerations in wave equation analysis of pile driving", Proc. Conf. on Application of Stress-Wave Theory to Piles, Sao Paulo, Brazil, Balkema, 41-46.
Davisson, M.T. (1972). "High capacity piles", Proc., lecture Series, Innovations in Foundation Construction, ASCE, Illinois Section.
Fellenius, B.H. (1999). APTLY e-mail archives.
Fellenius, B.H. (2001). "What capacity value to choose from the results of a static loading test", Fulcrum, The Newsletter of the DFI, Winter 2001, 19-22.
Goble, G.G. (2000). "Class A" capacity prediction", GRL + PDI Newsletter 36, February.
GRL and Associates, Inc. (1997). GRLWEAP - Wave Equation Analysis of Pile Driving, Manual, Cleveland, Ohio.
GRL and Associates, Inc. (1995). CAPWAP - CAse Pile Wave Analysis Program, Manual, Cleveland, Ohio.
Hannigan, P.J., Goble, G.G., Thendean, G., Likins, G.E. and Rausche, F. (1996). "Design and construction of driven pile foundations", Workshop manual, Publication No. FHWA-HI-97-014.
Holeyman, A., Maertens, J., Huybrechts, N., and Legrand, C. (2000). "Results of an international pile dynamic testing prediction event," Proc. Conf. on Application of Stress-Wave Theory to Piles, Sao Paulo, Brazil, Balkema, 725-732.
Lambe, T.W. (1973). "Predictions in soil engineering", 13th Rankine Lecture, Geotechnique, 23(2), 149-202.
Leroueil, S. & F. Tavenas (1981). "Pitfalls of back-analysis", Proc. 10th Inter. Conf. on Soil Mechanics and Foundation Engrg., Stockholm, ISSMFE, 1, 185-190.
Liang R.Y. & J. Zhou (1997). "Probability method applied to dynamic pile-driving control", Journal of Geotechnical Engineering, ASCE, 123(2), 137-144.
Rausche, F., G.G. Goble & G. Likins (1985). "Dynamic determination of pile capacity", Journal of Geotechnical Engineering, ASCE, 1985, 111(3), 367-383.
Paikowsky S.G. and Chernauskas L.R. (1992). "Energy approach for capacity evaluation of driven piles", F. Barends (ed.), Proceedings of Fourth International Conference on the Application of Stress-Wave Theory to Piles, The Hague, Balkema, 595-601.
Paikowsky S.G., Regan J.E., and McDonnell J.J. (1994). "A simplified field method for capacity evaluation of driven piles", Publication No. FHWA-RD-94-042.
Paikowsky S.G. and Stenersen, K.L. (2000). "Keynote lecture: The performance of the dynamic methods, their controlling parameters and deep foundation specifications", Proc. Conf. on Application of Stress-Wave Theory to Piles, Sao Paulo, Brazil, Balkema, 281-304.
Smith, E.A.L. (1960). "Pile driving analyses by the wave equation", Journal of the Soil Mechanics and Foundation Division, ASCE, 1960, Vol. 86, 35-61.
Stevens, R.F. (2000). "Pile acceptance based on combined CAPWAP analysis", Proc. Conf. on Application of Stress-Wave Theory to Piles, Sao Paulo, Brazil, Balkema, 17-27.
Svinkin, M.R., C.M. Morgano & M. Morvant (1994). "Pile capacity as a function of time in clayey and sandy soils", Proc. Fifth Inter. Conf. and Exhibition on Piling and Deep Foundations, Bruges, 13-15 June, Rotterdam: Balkema, 1.11.1-1.11.8.
Svinkin, M.R. (1996). "Soil damping in wave equation analysis of pile capacity", In F. Townsend, M. Hussein & M. McVay (eds.), Proc. Fifth Inter. Conf. on the Application of Stress-Wave Theory to Piles, Orlando, 11-13 September, Gainesville, University of Florida, 128-143,
Svinkin, M.R. (1997). "Time-Dependent Capacity of Piles in Clayey Soils by Dynamic Methods", Proc. XIVth Inter. Conf. on Soil Mechanics and Foundation Engineering, Hamburg, 6-12 September, Rotterdam, Balkema, 2, 1045-1048.
Svinkin, M.R. (1998). "Discussion of 'Probability method applied to dynamic pile-driving control' by Liang & Zhou", Journal of Geotechnical and Geoenvironmental Engineering, ASCE, 122(4), 319-321.
Svinkin, M.R. (2000). "Time effect in determining pile capacity by dynamic methods", Proc. Conf. on Application of Stress-Wave Theory to Piles, Sao Paulo, Brazil, Balkema, 35-40.
Svinkin, M.R. & R.D. Woods (1998). "Accuracy of determining pile capacity by dynamic methods", Proc. Seventh Inter. Conf. and Exhibition on Piling and Deep Foundations, Vienna, 15-17 June, Rickmansworth, Westrade Group Ltd, 1.2.1-1.2.8.
TNO Report, (1996). TNOWAVE and TNODLT, User Manual, Delft, TNO Building and Construction Research.
Can't find what you're looking for? Search here!
This entire site Copyright© 1997-2013 Don C. Warrington. All rights reserved. Website maintained by Positive Infinity and hosted by 1 and 1 Internet.
|
|
 |
|